Posted on: April 2, 2018

Road Resurfacing Update 04/02/18

The contractor will continue paving in Cedar Creek Subdivision today and tomorrow. They will move to Hill Flo Avenue tomorrow afternoon. After that they will move to Calcutta Court and Scott Street next. It is possible another crew will move in before the end of the week. If so they will begin widening on Oak Bowery From Wigdon Road to the bridge near the Grand National entrance. We will continue to update you as things change.