Posted on: August 16, 2019

Downtown Sidewalk/Intersection Updates

Downtown Sidewalk/Intersection Updates
DJI_0028


9th & Ave B: The work at the intersection of South 9th Street and Ave B is complete. These roads are now open to traffic.

 

9th Street: Beginning August 19, crews will be working on sidewalks on South 9th Street between Ave B and Ave C. Traffic will not be affected.

 

8th & Ave D: Beginning the week of August 19, crews will be working on sidewalks.

 

7th & Ave C: Beginning the week of August 26, crews will begin sidewalk and intersection improvements at South 7th Street and Ave C. Traffic will be limited.

Facebook Twitter Email

Other News in Home

OES COVID 19

OES ASKS RESIDENTS TO BAG ALL TRASH

Posted on: April 7, 2020
India Road Detour (1)

INDIA ROAD CLOSURE AND DETOUR

Posted on: March 16, 2020

ADEM PUBLIC HEARING AND QUARRY UPDATE

Posted on: February 21, 2020

Creekwood Resources - Granite Quarry

Posted on: January 27, 2020

ADA COMPLIANCE WORK UPDATE

Posted on: October 22, 2019

ADA COMPLIANCE WORK UPDATES

Posted on: October 11, 2019

Road Closure: South 8th Street

Posted on: October 10, 2019

Safer Shelters in Lee County

Posted on: April 18, 2019

Road Closure Update: 10th Street

Posted on: June 19, 2018

Road Closure: Fox Trail

Posted on: May 29, 2018
round about

Roundabout Video Tips

Posted on: April 9, 2018